Cancel or shorten a leave
A cancellation is a document with a reason on it. Once approved, it either removes the whole leave or ends it the day before he came back, and the days go back to his balance.
Before you start
- An approval route is required. Build one on the Approval screen for the process Leave Cancellation. Without one, the cancellation saves but nothing is given back.
- A leave whose leave year has closed cannot be cancelled. The balance it came from is gone.
- A waiting request is not a leave yet. Withdraw the request instead. See Apply for leave and get it approved.
Steps
- Open Leave Cancellation.
- Pick the Employee, then the Leave.
- Choose:
- The whole leave: leave Cancel From Date empty.
- He came back early: put the day he came back in Cancel From Date. It must fall inside the leave.
- Read Cancelled Days.
- Write the reason in Notes. It is required.
- Save, and send for approval.
Check it worked
- After the last approval, a whole cancellation removes the leave. A partial one ends the leave the day before Cancel From Date.
- Example: leave 20 to 24 April, back on the 23rd. The leave now ends on the 22nd and 2 days are back in his balance.
- If Payroll Attendance for the period was already made, remake it.
If it goes wrong
- Approved but the balance did not move - there is no approval route for Leave Cancellation. Build one and save the cancellation again.
- Refused: nothing to cancel - the days in that range were rest days or holidays the leave never charged.
- Refused: Cancel From must fall inside the leave - pick a date between the leave's first and last day.
- Refused: not found, or already cancelled - it has been cancelled before.
- The leave is not in the list, or the cancellation is refused because the quota was reset - its leave year has closed. Give the days back in the current year with an adjustment. See Correct an employee's leave balance.
- Cancel From Date set to the first day - that is a whole cancellation.