A half can keep targets and achievement apart: targets agreed in January, achievement recorded in July, on one sheet. The two dates on the half decide it. The achievement side does not open by itself when its date comes; HR opens it on the day with two changes and one button.

Who
HR (a PeopleNest administrator for the opening day)
Needs first
The round with its half, before sheets are issued

Before you start​

  • Decide this before issuing the sheets. Sheets take the half's dates when they are issued.
  • Ignore the Allow Target And Achievement Together tick. It is read by nothing. The dates are the mechanism.
  • There is no end date for the target window. Targets can be entered up to the day before the achievement window opens.

Steps​

At the start of the half

  1. On the half's line in Evaluation Cycle, set Target Window From to the day targets open. 05-Jan.
  2. Set Response Window From to the day achievement should open, and Response Window To to when scoring closes. 01-Jul and 21-Jul.
  3. Because the target start is earlier, the half is split. Activate and issue the sheets.
  4. Employees enter targets; their managers approve them. The achievement columns stay closed.

On the day achievement should open

  1. On the same line, change Target Window From to the same date as Response Window From. The half now counts as combined.
  2. Check the review days still leave the reviewers enough time.
  3. Press Apply Dates for that half.
  4. Reopen any sheet already submitted or approved for targets, so the employee can enter his achievement. See Send a sheet back or reopen it.

Check it worked​

  • In January, entering an achievement is refused with "This half keeps targets and achievement apart". That refusal proves the split took.
  • After the opening day, the same sheet accepts achievement.
  • Apply Dates lists any sheet whose dates were changed by hand. Those were skipped; fix them one by one.

If it goes wrong​

  • Achievement is open in January. Target Window From is blank or equal to the response start. Make it earlier.
  • Nothing opened in July. It never opens by itself. Do steps 5 to 8.
  • The client wants the target window to close in February and stay closed. Not possible. The target window runs up to the day before achievement opens. The nearest thing is to open achievement earlier.
  • One person's sheet still refuses achievement. His dates were set by hand, so Apply Dates skipped him. Fix his sheet's dates, or reopen it.